This document provides how to execute test plans.

정보

To manage test plans, you need a permission such as Project Manager, Create Plan/TC …, TC Execute. For more information, please refer to Global Permissions.

목차

참고사항

To execute the test plan, the following prerequisites must be satisfied.

  • You must change the status of test plan to

    상태
    colourGreen
    titletesting
    .

  • Before run the test, you must add a regression.

  • To add a regression the test plan must include at least one test case. 

...

  1. In TESTaide home, select a project that you want to execute.

  2. Select the 'Test Execution' menu on the left sidebar.

  3. In the test execution page, select a test plan that you want to add a regression.

  4. In the regression list panel below, click the ‘Add Regression’ button and enter the following information.

    • Test Plan Key* : The key of the selected test plan. (Fixed)

    • Regression Title* : The maximum length is 50 characters.

    • Environment : Test environment selected when creating the test plan.(If you want to change environment, you need to edit the test plan.)

  5. Click the ‘Save’ button at the bottom to complete the adding a regression.

...

Test Execution

정보

If your environment is a Selenium Hub :
When Selenium Hub is all busy and waiting, the user is notified.

참고사항

For the manual type of test plan, enter the results manually.

For the auto type of test plan, the results are entered automatically.

...

  1. In TESTaide home, select a project that you want to execute.

  2. Select the 'Test Execution' menu on the left sidebar.

  3. In the test execution page, select a test plan that you want to execute from the list.

  4. In the regression list panel below, click the ‘Run’ button.

...

Cancel an Execution

To cancel an execution,

  1. In TESTaide home, select a project that you want to execute.

  2. Select the ‘Test Execution’ menu on the left sidebar.

  3. In the test execution page, select a test plan that you want to execute from the list.

  4. In the regression list panel below, click the ‘Run’ button.

  5. You can see how the ‘Run’ icon in the middle of the run changes to the ‘Stop’ icon when the run is in progress.

  6. Click the ‘Stop’ icon to confirm the cancel pop-up window, click the ‘Yes’ button to complete the cancellation.

...

Test Execution Result

For the manual type of test plan

...

참고사항